Solution manager EWA report frequency

Former Member
0 Kudos

Hi all

In Solution manager we have early watch alert configured for weekly basis. But we need to change it to monthly basis.

In solution manager, when I execute solution_manager, and EWA reports I get reports for every one week. Where can i change this frequency?

Thanks

subbu

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member204746
Active Contributor
0 Kudos

EWA reports were designed to be run once a week. why do you want to run them only once a month? I don`t see any valid reasons...

Former Member
0 Kudos

I need to submit to operations team a monthly report. When i extract data from solution manager im able to get only four reports one per week. How can I combine all reports together into one single monthly report? Is there any possibility to automate this process?

Thanks

Subbu

former_member204746
Active Contributor
0 Kudos

Ok, I see...

I also submit a monthly report. I created a Ms-Word template based on a real EWA report.

I customized it for my own use.

but all these steps are manual and it usually takes me about 30 minutes to generate the report by fetching proper information.

so, go get the most important information from your EWA report such as disk usage, CPU usage, user count etc... and forget about the rest.