Hello SAP Experts

Iam currently working on versin 4.5B. In near future I will be working on an upgrade project for a client from 4.6 to ECC 6. Can somebody give me a brief on what activities are involved in an upgrade project and should I increase my skills by working on ECC 6.

If possible pl provide me with a link on the difference between 4.6 and ECC 6.0.

Thanks in Advance

Srikkanth

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

data becomes critical in an upgrde projct. so u need to be aware abt the migration tools like bdc and lsmw. for delta funtionality find the link

http://solutionbrowser.erp.sap.fmpmedia.com/

saurabh

Answers (3)

Answers (3)

Former Member
0 Kudos

plz find the high level design of the upgrade life cycle.

Activity

Description

SPDD adjustments (Adjustments in Data Dictionary objects)

Adjustment of data dictionary objects

Identify SPAU objects and Custom objects

Prepare the list of SPAU objects and Custom objects

Reassessment of effort for modification and adjustment activity

Reassessment of effort required for modification and adjustment activity

Object Tracking Sheet

Prepare the object tracking sheet

Modification and adjustments of

SPAU and Custom objects

Modification and adjustment activity

Object Testing (typically for custom objects)

Primary testing of object to avoid any short dump

QA Objects and documents

Quality Control of modification and adjustment

Release Request

Transport the request from DEV to QA system

Delivery of Objects to Client

Completed objects are delivered to the client

Integration Testing

Integration testing

Rework Objects

Objects requiring rework after integration testing by the client and receipt of feedback

Regards.

Former Member
Former Member
0 Kudos

Hi,

If it is a technical upgrade then you will have take care all your modifications like user exit and modification of Stndard access sequence and customzings. The data will not be affected.

Regards,

Murali