cancel
Showing results for 
Search instead for 
Did you mean: 

field is not populating in sales order

bcrao
Active Contributor
0 Kudos

Hi,

while entering sales order wbs element is not populating, is there any solution other than SHD0 and tab control, to visible in sale order

regards

chidambaram

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi,

You could make use of user-exit FORM USEREXIT_FIELD_MODIFICATION in include MV45AFZZ (via authorization objects, which you can assign in role customizing).

regards,

Siddharth

nisha_sharma1
Active Contributor
0 Kudos

Hello ,

Create requirement class and Requirement type relevalnt for your order type.

Path to create this is:

SPRO-> Proect systems->Material->Control of Sales-Order-Related Production->Check Requirements Classes

Check Requirements type also.

Create stretegy in view V_T461S.

assign req class &type to stgy.

then assign this req class and type in material master

create Project or WBS elemt in transaction CJ20N.

then follow the same process steps to create sales order that WBS elemt pop will come.

regards,

Nisha

@award pts is helpful.

bcrao
Active Contributor
0 Kudos

how to assign req class/type to MM and in which tab

regards

chidambaram

nisha_sharma1
Active Contributor
0 Kudos

Hello,

Assign requirement type and req class to Strategy in customzation.

Spro->Production-> Demand Management -> Planned Independent Requirements->

Planning Strategy

check under this node.

Then this strategy group to Mat Master in MRP3 TAB

try this.

Regards,

nisha

Former Member
0 Kudos

hai

Ask u r PS consulant to create wbs element and poject, then only it will pop

thanks

Former Member
0 Kudos

Hi Chidambaram,

Did you try using the user-exit of sales order MV45AFZZ ?

Hope this helps,

Erwan

former_member183879
Active Contributor
0 Kudos

Hi,

You may have to talk to your PS consultant.

If the material is linked to some WBS element or some activity type(which again is linked to some WBS element), then only the WBS element will be updated at the line item level in the sales order. However, the material's assignment to WBS element or the Activity type is configured in PS system in CJ20N.

Hope this helps you

Reward if this helps.