on 01-07-2008 4:39 AM
Dear PS Experts,
request kindly let me know history of project with regard to system status (Creation, Release, Teco, Close, etc) of a project in PS.
Is this data stored in table or available in any standard report of ps.
pl help
thanks in advance
regards
Srihari
Hi,
You have to pass the object number of the project, WBS , or nnetwork into JCDS. For getting the object number -
Project ID - Pass project ID into table PROJ and get object number of the project ID
WBSE- Pass WBSE No into PRPS and get object number of WBSE
Now pass the object number thereby obtained into JCDS and get the status history.
Hope this helps.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Further to my earlier posting, if change documents are activated in the system at project profile level & Network level, all changes to the project will be logged by the system. But since this takes a lot of system resources, consult your basis team before doing this.
Once change documents are activated all changes to the project can be captured using transaction:AUT10 -Evaluation of Audit Trail
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shrihari,
Status changes are stored in table JCDS
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.