Archived discussions are read-only. Learn more about SAP Q&A

bom ecplosion - cs11

hi,

i had created finish material P001 , THEN Swmifinish material B001, then raw material A001 .

then i create BOM (CS01) PA001 TP BA001 .

Then BA001 to RA001.

Now i want to explode this BOM through t code CS11 or CS12.

But it not exploding , showing message , BOM for P001 does not exist.

So IS THERE ANY PP SETTING FOR EXPLOSION THROUGH CS11 or CS13

Helpful Answer

by