Is there any option to raise/create Maintenance Order(PM Order) from Project???
if there... pls suggest me tht how to create it
Thanks,
Prakash.
Hi,
You cannot create a PM order from Project. You can link it to Project by entering either WBS or network activity on additional data tab page of PM order.
Hope this helps.