Float in cProject scheduling

Former Member
0 Kudos

What is a Float in cProject scheduling and how it works?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Karan,

The float is defined as time differnt between earlist dates and latest dates. Most simple example,

The project definition has:

must start constraints on Monday.

must finish constraints on Friday.

Under PD, there is a Phase, and under Phase there is a Task.

it has duration = 3 days.

After scheduling, the task will get a float = 2 days.