hi expert:

when I create purchase request from ps, the system generate the commitment in purchase request. the cost element 79000 is be determinated by system. how to config in customizing.

thank you !

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In material master (mm01) the valuation class for the material is maintained in the costing tab. This valuation class is mapped in "Automatic FI posting" (OBYC) in transaction BSX. Account determination is governed by this transaction.

Hemant

Former Member
0 Kudos

thank you

I got it

Former Member
0 Kudos

Hi,

Reward points if you found the answer helpful .