PS Material Strategy Group as 21 - reg

Former Member
0 Kudos

Hello,

For PS materials we are using planning material strategy group as 21.

Could you explain this clearly???????

purpose and need of 21 while running project MRP???

Speciality of 21 apart from other strategy groups(10,40 and etc)??

pls help me in this regard,,,,,

Regards,

Prakash.

Reward points for useful answer.............

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Strategy group of the material determines the requirement class of the material which inturn determines the account assignment, consumption account, special stock, etc.

Strategy group 21 is hard-coded for requirement class 80 which is for MTO project stock.

Quote from SAP documentation:

Quote begins:

"SAP has predefined strategy group 21 (with strategy 21) for the link

between sales documents and projects.

Notes:

If you do not maintain the strategy group for the material in the sales

and distribution document item, you cannot assign that item to a WBS

element.

Alternatively, you can assign the strategy group to a material using MRP

group 0021 (also predefined).

Requirements Classes

SAP has predefined requirements class 80 with account assignment

category D (assignment to WBS element) for the link between projects and

sales and distribution documents. Requirements class 80 is assigned to

strategy 21 using requirements type KP (also predefined). "

Quote ends:

Hope you find the information useful.

Muraleedharan.R

Former Member
0 Kudos

thanks Murali,

--Prakash