Hello,
For PS materials we are using planning material strategy group as 21.
Could you explain this clearly???????
purpose and need of 21 while running project MRP???
Speciality of 21 apart from other strategy groups(10,40 and etc)??
pls help me in this regard,,,,,
Regards,
Prakash.
Reward points for useful answer.............
Hi,
Strategy group of the material determines the requirement class of the material which inturn determines the account assignment, consumption account, special stock, etc.
Strategy group 21 is hard-coded for requirement class 80 which is for MTO project stock.
Quote from SAP documentation:
Quote begins:
"SAP has predefined strategy group 21 (with strategy 21) for the link
between sales documents and projects.
Notes:
If you do not maintain the strategy group for the material in the sales
and distribution document item, you cannot assign that item to a WBS
element.
Alternatively, you can assign the strategy group to a material using MRP
group 0021 (also predefined).
Requirements Classes
SAP has predefined requirements class 80 with account assignment
category D (assignment to WBS element) for the link between projects and
sales and distribution documents. Requirements class 80 is assigned to
strategy 21 using requirements type KP (also predefined). "
Quote ends:
Hope you find the information useful.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.