on 12-24-2007 6:15 AM
Hi SAP gurus,
In sales order, we carry out availability check. Suppose the ATP quantity is X. But after its delivery, the ATP quantity is not decreasing at the time of next check.
can You tell me what would be the reason and possible solutions?
-Prashant
Hi,
Check in OVZ9 or SD-BF-Availability check-Availability check against ATP-Carry out control for AC.
Check Include deliveries check box for the corresponding availability check and checking rule options.
Reward if helpfullllll............
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check avaliabailty check settings and aganist ur requiremnt type select material block for others. try this i am not sure, if it works ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Prashant
What checking rule you are following to the said plant?? Normally ATP check is controlled in OVZ9 where you define what requirements should be included while you run ATP check.
Thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.