on 12-24-2007 4:48 AM
Hi All,
Can anybody guide me on what are the settings required to create and explode a service BOM?
Regards
AK
Ayub,
1. You create Header material with genitem category group DIEN and itemcategory group ERLA or LUMF.(MM01)
2. You create sub components with item category group DIEN.(MM01)
3. Create BOM through CS01 T.code.
4. Define Itemcategory according to your requirement, the control of BOM Explode available in the Itemcategory throuh Bill Of material configuration data.
4. Set up itemcategory determination.
I hope it will helpfull for you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ayub,
A bill of material (BOM) describes the different components that together create a product. A BOM for a bicycle, for example, consists of all the parts that make up the bicycle: the frame, the saddle, wheels, and so on.
Process Flow
When you enter the material number of a bill of materials that is relevant for sales order processing, the system displays the material that describes the whole bill of materials as a main item. The individual components are displayed as lower-level items.
There are two ways to process a bill of materials in Sales. Once you have entered a bill of material in a sales order, the system runs pricing, inventory control, and delivery processing at:
- Main item level if the material is assembled, or
- Component level if the material is not assembled
The type of processing used by the system is determined by the item category group that you enter in the material master record for relevant materials.
Processing at Main Item Level
If you want the system to carry out pricing, inventory control, and delivery processing at main item level, enter ERLA in the Item category group field of the Sales: sales org. 2 screen in the material master record of the finished product. This means that the components only function as text items and are not relevant for delivery. The following graphic shows how a bill of material is processed at main item level.
Processing at Component Level
If you want the system to carry out pricing, inventory control, and delivery processing at the component level, enter LUMF in the Item category group field of the Sales: sales org. 2 screen in the material master record of the finished product. In this case, only the components are relevant for delivery. During processing the system automatically creates a delivery group. The latest delivery date among all the components becomes the delivery date for the entire delivery group.
Hope this helps you.
Do award points if you found them useful.
Regards,
Rakesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.