on 12-20-2007 9:52 AM
Hi,
We've just upgraded from 4.7 to ECC6. When running VA01, after we enter the sold-to-party we get the following error:
Date is in the past: Please check
Message no. VD399
I've checked around SDN and I haven't found any solutions. Any ideas as to what might cause this. Please note that the error message did not appear in 4.7 and we're using exactly the same master data
thanks
Michalis
Check SAP Note 980592
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We found the answer. It had nothing to do with that Note. There was a transaction variant for VA41 that had a delivery date defaulted in (don't ask me why). Every time you made any change to that contract, even though it had no delivery process, it kept notifying you about the dates. We removed the default date from the transaction variant and everything is ok now.
thanks for your help
Dear Michail Papadopoulos
Check your system date.
Regards,
Srikanthraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.