Need WBS split to AUC and Expanses during settlement (not %wise)

Former Member
0 Kudos

Hi,

We have some capital projects settling to AUC but we are also charging WBS for labor costs and travel expanses and offcouse capital costs.

Managment wants PS team to Settle labor/travel to CCTR and Capital cost to AUC. How can WBS recognize cost elements carry expanses and Capital Costs and split them during settlment?

expanse range: 500000-599999 travel/labor

Capital expance range: 600000-699999 to be capitalized

I will appreciate any clue in this regard.

-Atif

PS.: I am trying capital investment key at this time, so that WBS will settle only capital range in AUC.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Is your problem resolved?

Former Member
0 Kudos

Thanks Rakesh Pradhan & Hemant.

I havnt tested practically so far but its seems that this will solve my problem. I will let you know after tesing it.

Former Member
0 Kudos

Hi,

Maintain the allocation structure having two settlement assignments as AUC and Cost center. Define range of cost elements for both of these. i.e. source structure.

Hemant

Former Member
0 Kudos

Hi,

Maintain different settlement rule for WBSE with different recevier such as AUC & CTR. In settlement configuration define source structure such as CTR & AUC along with cost elements for settling the cost into different receiver.