We are facing problem in BOM transfer. After BOM transfer , system is generating two PRs for 1 material. In network component view , the material is appearing twice one with BOM item no 0000 and one with BOM item 0010. But material exists only once in BOM.
What may be the cause for this?
Regards,
Amit
Hi,
Please check SAP note:739440 has any relevance for you.
Quote from the note begins:
"You assign a BOM to a using Transaction CN33. When reassigning the BOM double requirements are created in the network.
Other terms
CN33, BOM explosion
Reason and Prerequisites
The "Alternative BOM" field on the selection screen of Transaction CN33 is the cause of the problem. It is set partly on initial or on 1. This should not make any difference, however, in the further selection the already assigned BOM is not recognized and thus assigned again.
Solution
Implement the program corrections as specified in the attached correction instructions
Quote ends
Muraleedharan.R
091 9880028904
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Does the material appear against two different activities?
If so , the referece point defined for the BOM transfer must have been defined for both the the activities.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.