Anyone could advice ..is there any standard report or table that can show Project and settlement
Thank you.
Nies
Hi Nies.
Usually you'd check CJI3 on the billing element. The sum has to be 0.00 if the settlement is successful. You will find the settlement postings in those cost element ranges that are defined in the system for settlement cost.
Another reort to check settlement is KE5Z and there MOC. It should also show a 0.00 for the billing element.
Best regards.
Jens