Table for Project code and Settlement

Former Member
0 Kudos

Hi All,

Could anyone advice me in how to find a table that can be shown data for project and settlement ?

Thank you so much

Nies

Accepted Solutions (1)

Accepted Solutions (1)

bettassoci
Explorer
0 Kudos

Hi Nies,

The following report will show you the sender, receiver, settlement distribution method (amount, percent), and settlement rule type... KOSRLIST_PR List of Settlement rules for Projects

What information specifically are you looking for?

Regards,

Kent Bettisworth

Former Member
0 Kudos

Hi Kent,

Appreciate for your advice. I am looking for the mass information of Project and WBS that has settlement rule(looking for report that can show Project-WBS and settlement rule inside). Normally, we use transaction code CJ02 or CJ20n to check the settlement rule.

It shows 'Display Settlement rule :Overview' (for example)

Cat:FXA

Settlement Receiver : 5000****

Receiver Short Text : ***

% : 100.00

Equivalance : 0

Amount :

Settlement : AUC/FUL

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

CJID gives line item settlement details for a given WBS. CN43 gives details of project ID and WBS details. I am not aware of any transaction which gives both, though it could be a gap in my knowledge.

Muraleedharan.R

091 9880028904

Former Member
0 Kudos

Nies,

For project definition, please check PROJ

For WBS elements, check table PRPS

For the settlement rule, tables COBRA and COBRB

For the settlement values, refer to the cost tables COSPD and COSSD.

I suggest you to refer to transaction RKACSHOW. This will lead you to all the cost tables for a particular object.

Hope this helps

Regards

Martina

Former Member
0 Kudos

Hi Martina,

Is there any standard report to shows project definition,WBS and settlement?

Thank you.

Nies

Former Member
0 Kudos

I don't think there's a standard one. But you can create simple custom report using Quickviewer (T Code SQVI) joining tables PRPS and COBRB.

Link the tables with fields PSPNR-PRPS and PS_PSP_PNR-COBRB.

Doesn't require much technical knowledge to create the report with selection criteria's and output parameters.

Regards

Sreenivas