Hi Expert,

When i have to create an order in the weekend, this message appear.

"Date 16.12.2007 is not a workday; last workday is 14.12.2007"

How can i eliminate this message.

Thanks for your help.

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

the message is depend upon the factory calendar settings,this is informative only you can still able to create on the specified date.

regards

thyagarajan

Former Member
0 Kudos

Thanks for your answer,

This message is not practical.

How can i delete it.

Where in the setting can i change the calendar.

former_member187991
Active Contributor
0 Kudos

hi

Factory calendar will be created by HR people and while creating the plant in enterprise structure the factory caledor will be specified.you can deactive the current date as basic dates for order, so you have to specify the dates while creating the maintenance order

regards

thyagarajan