on 12-14-2007 2:41 PM
Hi,
I use SAP ECC6, actually.
I created an internal network activity and I linked it a work center and an activity type.
When I run a report, every report, I don't see the costs relative to this network activity.
Please, could you help me?
Thanks a lot in advance
Regards
Hi,
Please ensure you have followed following steps:
1. Assigned cost center and activity type on costing view of workcenter. After this assignment when you assign work center to activity, the activity type gets automatically populated.
2. Maintain rate for activity type in Tcode KP26. Take help of your FI consultant.
3. If your system is not calculating cost during saving of project, you need to manually calculate cost. Click on activity and press CtrlF10 to calculate cost and CtrlF11 to display cost.
Hope this helps.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.