Network Costing in PS by period

former_member709139
Discoverer
0 Kudos

Is it possible to plan network activities in specific periods based on

the specific dates which are input as per Workforce Planning to

override the Basic Start and Finish dates on the Activity? For

example,

A network activity has a start date on Oct 1 and an end date of Nov

30. Thus this activity spans two periods.

6 hours of work are planned at 10 pounds per hour resulting in £60 plan

value.

In Workforce Planning, 5 hours are planned in October, and 1 hour is

planned in November.

Can the system be configured to use the weight of hours planned in each

period to form the basis of the planning resulting in £50 plan in

October and £10 plan in November? Currently, I cannot find a way to

influence this via standard configuration for PS, Workcenters, etc.

Distribution keys seem limited in that they are based on percentages only and there doesn't appear to be a setting to use actual date planning to drive the calculations.

I have heard that there is functionality for products such as XPM or

cProjects that may have enhancements in this area which could prove

useful if there is no standard config in ERP to influence this.

Thanks,

Kevin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Kevin,

The best way would be to create your own distribution key and use it.

Go to KP80 and create User Defined==> Independent key

Input the factor for all relavant periods:

In your case:

Period (for Calander yr) Factor

10 5

11 6

Ravi Shrivastav