on 12-14-2007 6:49 AM
Hi all,
Please advice . Is there any tcode to mass unteco for network under a project ? without going line by line in project builder? or open the project one by one?
Please advice.
Thank you.
Nies
Nies,
I´m afraid there is no such tool. It is not possibile to affect status via mass maintenance actions.
In the project builder you can consider selecting all the networks from a single project in the network overview and changing the status of all of them together.
You can reach this network overview from the Project Definition detail screen.
There is no such workarround for networks belonging to different projects.
I hope this clarifies.
Best regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There is no standrad transaction code available for changing the status. You can follow any of the metho with help of ABAPer
1. LSMW: Record the LSMW for changing the status.
2. BAPI can be used for this purpose.
Hope this will help you.
Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.