We configured Planned Order integration model to show up R/3 planned orders as SNP Planned orders in APO. However when the planners on R/3 side intervene the orders in terms of some of the fields, it passes on to APO as a planned order without source of supply. This is due to the design, the PPM information is manually maintained in APO and is out of sync with the information in R/3 side. The system thus chooses to keep a blank source of supply for the orders rather than redetermining the source of supply in APO. From some of my recollections, I understand that there are ways to run a report in APO that redetermines source of supply for planned orders with blank source. Can someone pass on this report information to me ? (We do not want to run user exits/BADIs to do this determination, and rather would prefer a standard report)

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

What happens if , after your PPM is synched, you delete the orders in APO and re-Cif it from R3?

not sure of the report but i thought you can re-run the heuristics and get the SoS again but not sure if it will work with a order created in R3

srinivas_krishnamoorthy
Active Contributor
0 Kudos

It is by design that PPM is not synced. There are tens of resources in R/3 side which we have summarized and kept as a "aggregate" resource data in APO manually. So there is no point in deleting APO orders and re-CIFing. It is by design that the orders come into APO without source of supply. Some of these orders are NOT solver dependent and is manully managed by planners in R/3 side. So we do not want to run the solver to change that data. We just want the PPM to be picked up in APO so that we can correctly load the resources.