on 12-12-2007 9:06 AM
Hi,
I want POC, BCWS, to be displayed in transaction CNE5...but all tables are showing values Zero. I have done following customizing settings,
1.Maintain Progress Version
2.in Progress version, POC weighting is weight(active project)
and EV Basis is Cost Plan.
3.Define Statistical Key figure for Percentage of completion.
4. Maintain Value Category
5. Assign SKF to value Category
6. Maintained Measurement method in progress in CJ20n.
7. Mentioned POC weighting.
8. Network is confirmed.
9. Run CNE1
10. in CNE5 profile taken is EVA
is there any step missing.
Thanks & Regards
Pravin Desai.
Hi Pravin.
Just a short guess without digging deeper: Did you do a project settlement before doing the progress analysis? Data is coming from the project info data base...
Best regards.
Jens
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pravin.
It depends on the messurement method. The 0 progress might be the right output. Possible sources of errors:
Check the status of the project in released.
Check if you have done allocations on the network/project structure.
Rebuild project data base (CJEN).
Have you assigned a cost element group to the progress method?
Best regards.
Jens
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.