Hi Experts,
Is there any transaction code for assign wbs element to G/L and cost center. Its very urgent.
Thanks in advance.
Chandra
It is solved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In TCode CJ20N, on Basic Data tab page of WBS element under responsibility subtab you can mention cost center. This I suppose must be only for reporting purpose. Please check if it is useful to you.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is possible through configuration. You define strategy to create this automatic settlement rule, then apply this to the project profile.
Then you have to run CJB1 or CJB2.
However, as of EHP3, you can also use the BAdI WBS_ SETTLEMENT_RULE_NEW to pass on settlement rules to WBS elements with existing settlement rules. |
Hi Chandra.
In Transaction CJVC you assign cost centers to value categories. In SPRO you follow the path Project System --> Cost --> Value Categories to maintain the project settings. Please follow through the instructions on cost allocation and settlement carefully to allow an automatic periodical settlement of your projects. You will find additional help to create your needed business case on help.sap.com.
Best regards.
Jens
Message was edited by:
Jens Schmid
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.