once creating WBS element using the transaction code CJ20N and i want to automatically pick the correct WBS element in sales order account assignment overview.the WBS element is defined depend on the material ?so how we are able to link this ?is it possible or not? if possible help me out my dear SAP Professionals...

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

For manually assigning a sales order line item to WBSE, certain conditions should be satisfied. Requirement type and class of the line item should be such that account assignment category (D) and consumption (P) shall be maintained. For this the approrpriate item category and scheduled line should be selected / customized.

Muraleedharan.R

091 9880028904

Former Member
0 Kudos

THANKS ALOT MURALEEDGHARAN

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

This Is possible if you create (trigger the Project in the Background )when you are creating the sales order.otherwise you need to assign the WBS element in the sales order so that only link will be established between them.

I hope this clarifies your quiery and hence reward me points

Thanking you,

Best Regards,

R.Srinivasan

Former Member
0 Kudos

sales doc - header - acc assignment - wbs element