on 12-11-2007 8:58 AM
Hi,
I have to do network/activity confirmations through the transaction CN25 in FI System. For doing this confirmation through CN25 in the FI System what all data from the HR System needs to be present in the FI System?
Thanks & Regards,
Soumya.
Hi,
In order to do activity confirmation (CN25), HR master data should be available & assignment of employee to network activity through work centre.
In costing sheet (KP26), hourly rate for the activity types assigned to work centres & cost centre should be available.
Hope this will help you.
Regards,
Rakesh Pradhan