Hi!
My requirement is to schedule the network and, conseguentely the wbs, within the dates provided in material component (requirements date).
I have a scheduling with "network determine date" with operation date
Can you help me?
Thanks & Regards,
Raffaele
Hi,
In case of network determine dates, scheduling of the project will take place considering the dates from network & in turn WBSE can also be scheduled. But the requirment you are looking for considering the material requirment may n't happen as on assignment of material components to project, material requiment date will be derived from network activity date (where material is assigned) considering scheduling scenario such as back ward / forward.
If material requirment date is predefined you can go for backward scheduling of the project. Free scheduling scenario may also help you.
Hope this will help you.
Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If all the material components attached to a given activity have the same requirement date, it is better to define that date in the activity concerned as a constaint. - mabe "must finish" constraint.
Then you can do appropriate scheduling as explained by Rakesh to achieve the scheduling objectives.
Muraleedharan.R
091 9880028904
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.