Confirnmed Qty is '0'

former_member315051
Active Contributor
0 Kudos

Hi Friends

va01 schedulelines tab page system is showing that confirmed quantity is ' 0' ,the stock is avilable and i have activated schdulelines allowed indocator in Item catarory document.

can any one look into this pls

Waiting for reply

Accepted Solutions (0)

Answers (6)

Answers (6)

former_member315051
Active Contributor
0 Kudos

.

Former Member
0 Kudos

hi,

go to mmbe transaction code and check the material movement in the environment tab. or double click on the storage location and view whether the material has been blocked for some other sales order.

REgards,

Murali

Former Member
0 Kudos

Hi,

pl check the plant from where sales is to be carried out and check if the customer is assigned to this particular plant.

if this answers ur query, do assign points.

AMla

bcrao
Active Contributor
0 Kudos

Hi,

check the plant determined in sales order and stock available

krishnaswamy_kumaraswamy
Active Participant
0 Kudos

spro->sales distribution ->basic functions->availability check ->rule based availability check ->assign buissness transcation to sales order type

check whether this setting is done

krishnaswamy_kumaraswamy
Active Participant
0 Kudos

do the avalb check

check what you have given in the avlb in material master( Kp no check , give 01 or 02 )

check what you have given in MRP in material master ( if ND (no planning ) remove and give PD )

reward if it helps