i am deva

what are the steps are involved in sap project implmentation in a orgn?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

The ASAP methodology is recommended by SAP for implementation planning and system implementation. It has the following phases.

Project Preparation - The primary focus of Phase 1 is getting the project started, identifying team members and developing a high-level plan.

Business Blueprint - The primary focus of Phase 2 is to understand the business goals of the company and to determine the business requirements needed to support those goals.

Realization - The purpose of this phase is to implement all the business and process requirements based on the Business Blueprint. You customize the system step by step in two work packages, Baseline and Final configuration.

Final Preparation - The purpose of this phase is to complete testing, end-user training, system management and cut over activities. Critical open issues are resolved. Upon the successful completion of this phase, you will be ready to run your business in your productive R/3 system.

Go Live and Support - Transition from a project oriented, pre-productive environment to a successful and live productive operation.

Def:The Accelarated SAP is the implementation solution provided by SAPwhich integrates several components that works in conjunction to support the rapid and efficient implementation of the PROJECT.

PHASES IN ASAP METHODOLOGY

1.Project Preparation

2.Business Blue Print

3.Realization

4.Final Preparation

5.Go-Live and Support.

1.PROJECT PREPARATION WE HAVE 8 STEPS.

1A.SCOPE OF PROJECT

1B.PHASES INVOLVED

1C.SYSTEM LANDSCAPE

1D.TEAM FORMATION

1E.DEADLINES OF THE PROJECT

1F.BUSINESS PROCESS DOCUMENTS (OR) BUSINESS REQUIREMENT

SPECIFICATIONS

IN 1F AGAIN WE HAVE 5 STEPS....Pls dont get confused.

1F ->A1-REQUIREMENTS OR EXPECTATIONS

A2-GENERAL EXPLANATIONS

A3-SPECIAL ORGANIZATIONAL CONSIDERATIONS

A4-CHANGES TO EXISTING ORGANIZATION

A5-DESCRIPTION OF IMPROVEMENTS

1G-TECHNICAL REQUIREMENTS

1H-KICK-OFF MEETING

2 BUSINESS BLUE PRINT . IN THIS WE HAVE 8 STEPS

2A.ORGANIZATIONAL STRUCTURE

2B.DATA COLLECTION SHEETS

2C.DATA CONVERSION STRATEGY

2D.BUSINESS BLUE PRINT DOCUMENTATION

2E.CUSTOMIZATION

2F.ESTIMATION OF DEVELOPERS

2G.COMMUNICATION STRATEGY PLAN

2H.DEVELOP THE SYSTEM ENVIRONMENT

2I.USER ROLES AND AUTHORIZATIONS.

3. REALIZATION . HERE WE HAVE 7 STEPS.

3A.ORGANIZATIONAL CHANGE MANAGEMENT

3B.BASELINE CONFIGURATION & CONFIRMATION

3C.UNIT TESTING

3D.FINAL CONFIGURATION AND CONFIRMATION

3E.FUNCTIONAL SPECIFICATIONS.IN 3E , WE HAVE 3 STEPS AGAIN...

3E1.SOLUTION INFORMATION

3E2.OBJECT INFORMATION

3E3.REVISION HISTORY....WE HAVE 12 STEPS HERE .....

3E3A.DESCRIPTION AND PURPOSE

3E3B.BUSINESS PROCESS DETAILS

3E3C.CURRENT FUNCTIONALITY

3E3D.EXPECTED FUCNTIONALITY

3E3E.SAP SITUATIONAL ANALYSIS

3E3F.ADDITIONAL INFORMATION

3E3G.FORMS

3E3H.REPORTS

3E3I.INTERFACE

3E3J.DATA MAPPING

3E3K.APPROVAL AND MODIFICATION HISTORY

3E3L.ADDITIONAL ATTACHMENTS.

3F.TESTING THE PROGRAMS

3G.PREPARING THE ENDUSER DOCUMENTATION

4.FINAL PREPARATION

WE HAVE 4 STEPS.....

4A.UPLOADING THE STIMULATED DATA

4B.INTEGRATION TESTING

4C.CUTOVER ACTIVITIES

4D.PRE GO-LIVE END USER TRAINING

5.GO-LIVE AND SUPPORT

SIGN-OFF MEETING

CHAN

Former Member
0 Kudos

Hi ASAP Steps

Phase 1: Project Preparation - The purpose of this phase is to provide initial planning and preparation for your SAP project.

Phase 2: Business Blueprint - The purpose of this phase is to achieve a common understanding of how the company intends to run its business within the SAP System. The result is the Business Blueprint, a detailed documentation of the results gathered during requirements workshops. The Business Blueprint document represents the business process requirements of the company. It is the agreed statement of how the company intends to run its business within the SAP System.

Phase 3: Realization - The purpose of this phase is to implement all the business process requirements based on the Business Blueprint. The system configuration methodology is provided in two work packages: Baseline (major scope); and Final configuration (remaining scope).

Phase 4: Final Preparation - The purpose of this phase is to complete the final preparation (including testing, end user training, system management and cutover activities) to finalize your readiness to go live. The Final Preparation phase also serves to resolve all critical open issues. On successful completion of this phase, you are ready to run your business in your live SAP System.

Phase 5: Go Live & Support - The purpose of this phase is to move from a project-oriented, pre-production environment to live production operation.

Additionally:

Some additional Infomation on ASAP methodology:

Phase 1 - Project Preparation

Change Charter - Goals and objectives of Organizational Change Management

Project Plan - This is a first cut focusing on milestones and Work Packages; details to come.

Scope - Sets the initial definition of the project; input from sales cycle.

Project Team Organization - Sets the who of the project: Standards & Procedures - Sets the why and how of the project.

Phase 2 - Business Blueprint - Requirements reviewed for each SAP Reference Structure item and defined using CI Templates (in the Q&Adb). Business Blueprint - This is the output of the Q&Adb and is the key document for Phase 3.

Phase 3 - Realization - Master Lists - Define business scenarios and R/3 transactions to be realized in the system. BPP - Business Process Procedures representing R/3 transactions; used for unit testing & documentation. Planning - Defines how the configuration will be done and how it will be tested. Development Programs - Provides details of the external programming requirements. EU Training Material - End User training material and process documentation.

Phase 4 - Final Preparation Stress & Volume Tests - Plans for confirming the production hardware’s capabilities

Cut over Plan - The details of how to move to the production environment and go live

Conduct End User Training - Delivery of the necessary levels of R/3 End User training prior to going live

Phase 5 - Go Live & Support: Ensuring system performance through SAP monitoring and feedback.

<b>For further details on ASAP make small search insdn