Hi all GURU,

I have some questions regarding QM:

1) At the time of UD in QM, at a time can we do material transfer to more than one material?

2) Can we directly do UD without result recording? For RM we dont result recording but depending upon test certificate provided we distribute material.

3) Is it possible to have stock transfer tab even for inprocess inspection (though its not require logically, want to know to confirm it).

Please help to find answers of above questions, right help will be rewarded.

Thanks and regards,

Devang

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

UD is possible without result recording,

In material master's QM view activate skips allowed check.

Answers (3)

Answers (3)

Former Member
0 Kudos

Can use this FM-EXIT_SAPMQEVA_001

Try and come back.

Message was edited by:

Rajesha Vittal

Former Member
0 Kudos

1) UD for different material possible try -user exit -QEVA0001

2)Yes with out RR you can do UD, no other setting required

3)No, cannot have ST tab for inspection type 03.

Message was edited by:

Rajesha Vittal

Former Member
0 Kudos

Hi consultant,

Ans 1 : At a time we can not do material transfer to more than one material.

Ans 2 : We can directly do UD without result rec.For that go to material master- QM view- insp set up.There is indicator "Check char", Dont set this indicator.

Ans 3 : It's not possible to have stock transfer tab even for inprocess inspection.

Message was edited by:

sandip raut