cancel
Showing results for 
Search instead for 
Did you mean: 

How to change material type

Former Member
0 Kudos

Hi,

I want to change the metrial type.Hope its possible using t code MMAM, and can anybody pls confirm is it possible to change Raw material to Semi finished?

Regds

Accepted Solutions (1)

Accepted Solutions (1)

bcrao
Active Contributor

Prerequisites

If you use the material ledger, the material must be settled in it.

If the old material type did not require you to specify a price control (for example, standard price or moving average price) for the material, the new material type must not be configured such that it allows only standard price as the price control.

If the material has been maintained from the Production Resources/Tools view, this view must also be allowed for the new material type.

If the material is not a configurable material, the new material type must not be allowed only for configurable materials.

In Customizing for the Material Master (in Define Attributes of Material Types), the following indicators must have the same setting for the old material type and for the new material type:

Material for process indicator

Manufacturer part indicator

If inspection plans are required for quality management inspection of the material, they must be allowed for the new material type.

The Material type ID indicator (presently used only in Retail) must be the same for the old material type and for the new material type.

If the material is already in stock, or if reservations or purchasing documents exist for it, the following conditions must also be met:

The stock values of the material of the new material type must be updated in the same G/L account as the stock values of the material of the old material type.

Quantities and values of the material of the new material type must be updated in exactly the same way in all plants as quantities and values of the material of the old material type.

If there is a transfer requirement for the material and if quants of the material exist, the new material type must also allow the material data to be maintained from the Warehouse Management view.

If the material, whose material type you want to change, was handled in batches and if, due to the maintenance statuses of the new material type, the material can no longer be handled in batches, although batches still exist, you cannot change the material type.

Answers (1)

Answers (1)

Former Member
0 Kudos

yes,you can change material type using this code.If you want change raw material to semi finished goods then you need to extend some views.

former_member417490
Participant
0 Kudos

Hi ,

You could change Material type from Raw Material to Semifinished Goods ,but before that make sure that you don't have any valuated stock at plant level. As due to this you may not be able to change as account determination for the two material types differs.

With Regards,

Siddhartha Chatterjee