on 12-05-2007 5:50 AM
Hi
I want the configuration steps completely for returns from customer with integration of QM
hi kiran,
complete the order to billing cycle.
then do the returns process.for this returns process u need to configure 3 storage location for one plant.
1st sloc for goods for delivery
2nd sloc for goods for inspection
3 rd sloc for scrap goods
after the post goods receipt in returns delivery post these goods through mb1b t-code using 453 movement type to 2nd sloc. if the goods pass the quality test post it to 1st sloc other wise transfer to 3 rd sloc
regards,
ramky
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi kiran,
give issue storage location is first stiorage location. because u have been entered first storage location in returns delivery.
regards,
ramky
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to the link , select Q34 building block
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.