Responsible Cost Center on WBS (cj20n - project builder)

Former Member
0 Kudos

Dear All,

We normally put responsible cost center in our each WBS. However, it takes time if we put one by one in each WBS. How can we make that we only need put in first level WBS then all WBS under 1st level will follow the responsible cost center. Please advice.

Many thanks in advance.

Nies

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You may want to post this on FI. CO folks do a lot of work with PS

Answers (0)