Dear Guru's,
I am working in the SRM 5.0 version and its Extended Classic Scenario. I have successfully created a Purchase order locally as well as in the backend, but when i am trying to do the Confirmation through "Centralized Purchasing --> Confirm Goods/Services centrally" and when doing the Confirmation, the process is confirmed and when checked in BBP_PD the status is Created, complete, confirmed.
But when i go to the Backend system and check in the WE02 i am getting the following error (51):
Incorrect doc.no.: $ 1 . Select document number between 5000000000 and 5099999999
And the Diagnosis shown is:
The document number you specified, "&v1", is not in the appropriate number range. The number range is dependent on the document type.
With this i can understand that there is error with the Number ranges, can anyone help me in solving this issue. The menu path for assigning the document number will be helpful, if i am not wrong. Points will be surely rewarded.
Thanks in Advance,
Mohit.
In R/3 go to SPRO > Materials Management > Inventory Management and Physical Inventory > Number Assignment > Define Number Assignment for Material and Phys. Inv. Docs
Make sure that your material document interval number range is set to internal (ie. not flagged as external).
Then do a new confirmation in SRM. It should reach R/3 successfully.
Neil