In the configuration of payment term, there are four criteria for baseline date:

no defalut date; entry date; docuemnt date; posting date.

For SD receivable items, what the "entry date" and "docuemtn date" respectively stand for when calculate the open item receivalbe due date? Does "document date" mean billing docuemnt date or order date?

Thanks for your explanation!

Justin

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Justin

Document Date is the date on which you do a particular transaction. It is neither order date nor billing date.