on 11-29-2007 7:56 PM
Hi everyone,
Is there step missing somewhere between 1 and 3?
1. tester - marks change request to Successfully Tested
2. change manager - changes maintenance cycle to Emergency Correction, then to Go-live
3. it operator - schedules the transport requests into Production
I get an error that my transport log that my transports have not been approved to go into production and I'm wondering what I am missing.
thanks,
Jason
Hi Jason,
you need to execute the action 'Released to Production' which will set the status 'Authorized for Import'.
Regards,
Kriti Bhalla.