Actually in my project iam using 10 activities to get one FERT item.

Proj Def:CNC M/C

L1WBS

L2WBSE-1:Design

L2WBSE-2:Purchase

L2WBSE-3:Assembly

For Design WBSE iam using 10 activities,here for each activity iam attaching one BOM,

again in Purchase WBSE iam using same 10 activities for just information of PO completion for tht particular BOM.

and for Assembly WBSE also iam assigning same 10 Activities for assembling .. Ok..

Now once i release the Project ,then PR's will raised for all BOM's..Ok...

thn after once PO's completed for these all ten activities.

Based on this all 10 activitis in Purchase WBSE want to get confirm automatically.

Same process for Assembly WBSE also..

Is thr any option for auto confirmation of activities???????if its thr pls let me know.

Pls help in this regard...................

---Prakash.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Rakesh,

Thanks for your information...

--Prakash.

Former Member
0 Kudos

Hi,

As per standard SAP, there is no automatic confirmation of activity based on procurment process. For confimration activity various methods are available such as time entry in CATS / through External system / transaction codes cn25 /27 etc. Some kind of enhancment is required for automatic acitivity confirmation. You may need help of ABAPer in this. In Confirmation node of configuration, there is enhancement of confirmation.

Automatic confirmation of activity functionality is n't available in standard SAP. This has also certain logic. Let us say in WBSE for design, how system will identify the confirmation of the tasks & some input is required for this. Morever activities are defined by user only & it is also n't an account assignment object.

Hope this will help you.