Hi,
Our client don't want to use PP module. So BOM and Routings are not available. But he wants cost estimate , costing run and costing from SAP. Without BOM and Routings how can i configure the Product Costing. Please guide me. It is very urgent.
Thanks Harish,
My mail Id: sateesh.veluguri@mytecsoft.com
It is urgent Please
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I am also providing the steps for the same for all to have a glance of it and can be made use of at some point of time.
Transaction Details
KKPAN Create cost estimated for the product. This will include material and activities as required by you.
CK24 Mark and release your cost estimate.
KKF1 Create a CO production order
KKF4 Release cost estimates for the production order
KKF2 Release the production order
MB1A Issue material to the production order.
KB21N Activity confirmations for the order.
MFN1 Revaluation of order for actual activity prices
KGI2 Actual overhead calculations.
KKAX WIP calculations.
KKS2 Variance calculations.
MIGO/MB31 Goods Receipt from the Order.
KKF2 Technical completion of the order.
KO88 Order Settlement
Hari
Hi Sateesh
Product Costing can be performed without PP,by using Cost estimate without Quantity structure,send me your mail ID I will forward some documents on it,which I feel might be useful to you at this point of time.
Hari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.