more than 1 dem version active for mrp

Former Member
0 Kudos

Hello All,

I'm in ECC 6 and I've created two active demand plan version for the same material. I've run MRP both single and total: the system plans both versions.

From what I know, only one version can be run by MRP at time. (sap documentation!!)

Any tip?

regards

Nue

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

MRP will run & consider all active versions .

If you do not want any version , you can deactivate .

If it is simulative planning ie LTP Run you can specify the version.

Regards

YMREDDY

Former Member
0 Kudos

If both versions are cative then both versions will be considered in MRP, hence decativate one varsion and run MRP...it will consider only one demand.