HI,Release Prerequisites.

Former Member
0 Kudos

Hi,

I need to set up a release stragegy, the no of codes are

01 - Buyer 1

02 - Buyer 2

03 - Manager 1

04 - GM 1

05 - GM 2

06 - GM 3

My requirement is the following combination should be possible for releasing a document .

01 / 03 / 04

01 / 03 / 05

01 / 03 / 06

02 / 03 / 04

02 / 03 / 05

02 / 03 / 06

Could anyone help me in sending the release prerequisite setting how to process the above functionality.

Regards,

DilliB

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dilli,

I still believe your strategy is going to work..

What I understand is

Buyer 1 manager 1 , GM 1 ,

Buyer 1 manager 1 , GM 2 and Buyer 1 manager 1 , GM 3 ,

Similarly,

Buyer 2 manager 1 , GM 1 ,

Buyer 2 manager 1 , GM 2 and Buyer 2 manager 1 , GM 3 ,

WHere i see an issue is the classification chracteristic. Is it going to be the same or could be different for both buyers.

If it is just one, it is not going to work, else it should unless what I understood above is incorrect.

Former Member
0 Kudos

Dilli,

The post by Batchu explains it absolutely. Would yu let us know if you have issues after referring the link.. Moreover the charcateristics/ Release criteria you'd be working with will also be a question

Former Member
0 Kudos

Hi Pawan,

Thanks for your response,

My question is not about the configuration of RS, but i need to configure the level of releases as per the business scenario but there lies a crux in the release prereuisities configuration.

Hope you could be able to understand that the RS is not a big issue when the level of release codes are within 3 levels, when it exceeds and more than one code exists in the same level, how to handle such scenario ? This is my question.

Pl help.

Regards,

DilliB

Former Member
0 Kudos

Hi,

I got your point,what i understood is, the same classification you want to have different strategies.it isnot possible to have two strategies with same classification.

The only possibility is you must have to make the difference in those charecteristics.

if you can explain what are the charecteristics you are using then we ssall suggest some thing

one more suggestion why can't you make those two codes(01,02) to one,if there are any document type issues(both have different document types only to work)then you can make the charecteristics in classification differenetly then you purpose will solve.

I think you understand with this.

please update with furher posts to make this issue close.

Regards,

Batchu.

Former Member
0 Kudos

Dilli,

To start with, It depends on whether you are working with or w/o classification.

Anyways,

1. Assign the 6 release codes as mentioned c1, c2 ,c3 ,c4 ,c5, c6

2. under Release indicator assignment, do the following

S1 X- code 1( buyer 01) - blocked

S1 X- code 1, Rel indicator as desired

S1 X- code 1, Code 3- X- Manager, Rel indicator as desired

S1 X- code 1, Code 3- X- Manager, Code 4- X-GM1,Rel indicator as desired

S1 X- code 1, Code 3- X- Manager, Code 5- X-GM2,Rel indicator as desired

S1 X- code 1, Code 3- X- Manager, Code 6- X-GM3,Rel indicator as desired

S2 X- code 2( buyer 02) - blocked

S2 X- code 2, Rel indicator as desired

S2 X- code 2, Code 3- X- Manager, Rel indicator as desired

S2 X- code 2, Code 3- X- Manager, Code 4- X- GM1,Rel indicator as desired

S2 X- code 2, Code 3- X- Manager, Code 5- X- GM2,Rel indicator as desired

S2 X- code 2, Code 3- X- Manager, Code 6- X- GM3,Rel indicator as desired

3. Under Release indicator Prereqs

S1 01 Buyer 01-Code 1- X

S1 03 Manager-Code 1- + , Code 3-X

S1 04 GM1- Code 1- + , Code 3-+, Code 4 -X

S1 05 GM2- Code 1- + , Code 3-+, Code 5 -X

S1 06 GM3- Code 1- + , Code 3-+, Code 6 -X

S2 02 Buyer 02-Code 2- X

S2 03 Manager-Code 2- + , Code 3-X

S2 04 GM1- Code 2- + , Code 3-+, Code 4 -X

S2 05 GM2- Code 2- + , Code 3-+, Code 5 -X

S2 06 GM3- Code 2- + , Code 3-+, Code 6 -X

Simulate and see if it fits..

Former Member
0 Kudos

Hi Pavan,

Thanks for your reply,

We are using the RS with classification.

I am bit confused with your step 2, as because under the release indicator configuration node in the SAP, there is no option to do the assignment between Release ID and the release code.

Could please ellaborate a little

Regards,

DilliB

Former Member
0 Kudos

Hi,

please follow the link below,

http://www.sap123.com/showthread.php?t=59

for more information.

stil have doubts please let me know

reward if usefull

Regards,

Batchu