how to proceed mrp

hi gurus

i have maintained the plant parameters and i have activated mrp in material master, but iam not able to run mrp in md02

i have created the outline aggreement also

pls tell the things what i have to do at this stage

thanks and regards

RAM

Former Member
Former Member replied

Ram,

check the stock at MD04 and create a reservation and more than stock available.

for schedule agreement activation,prerequists are

your procurement type should be 'F' in material master

maintain the agreement in source list

while running in MD02,In the planning mode select 3(delete and recreate planning) and enter.

it will work,if not please let me know