Hi,
How to restrict the PR and RFQ up to the target quantity as a reference. The PR and RFQ should not be available, after the target quantity as a reference.
Thanks in advance
Vikram
Hi,
we can create the PO with reference to PR or RFQ, once PO is created for the quantity in the PR or RFQ these should not be used again as a reference.
Regards
Vikram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do you meant to say making the PO with referance to PR,and the qty should not exceed the PR qty, then you have to make as Error for message 06076 in SPRO-MM-Purchasing-Environment-systemmessages.
if this is not you are looking for please let me know.
Reward if usefull.
Regards,
Batchu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.