PR and RFQ usage upto the target quantity

Former Member
0 Kudos

Hi,

How to restrict the PR and RFQ up to the target quantity as a reference. The PR and RFQ should not be available, after the target quantity as a reference.

Thanks in advance

Vikram

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

we can create the PO with reference to PR or RFQ, once PO is created for the quantity in the PR or RFQ these should not be used again as a reference.

Regards

Vikram

Former Member
0 Kudos

Hi,

activate the error message that i told you before and check it should fit for you requirement

Please let me know.

Regards,

Batchu

Former Member
0 Kudos

Hi,

Do you meant to say making the PO with referance to PR,and the qty should not exceed the PR qty, then you have to make as Error for message 06076 in SPRO-MM-Purchasing-Environment-systemmessages.

if this is not you are looking for please let me know.

Reward if usefull.