Dear All,
We have a situation here where none of the change runs are proceeding in production. All change runs are getting terminated.
i have checked in RSA1> tools>attr/hier. In here I see objects are locked in the infoobjects list and there is no save button. If I checked in CHANGEUNMONI , I see change run is executing and the list of info objects to be activated.
I checked the table RSDDAGGRMODSTATE for entries that has CLOSEDFL blank.
Iam not sure how to release the lock that change run has created.
Checked SM12 and SM37. none of the change runs running.
Please suggest.
Regards
Srini
Message was edited by:
Srinivas
Hi,
Try to run the change run job once again , unless it is repeated and completed successfully , the lock will not release.
Once the change run job gets completed successfully, all locks will be released.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.