Dear All,

I have a strange requirement for a material which is having Procurement type ' X '.

The scenario is like that the material is having requirement of 1000 Pcs. with a quota of 50% for In-house mgf. & 50% for external procurement i.e. 500 pcs. will be manufactured in-house & rest 500 pcs. will be procured externally.

Now for external procurement of 500 pcs. we are having two vendors :

To one vendor we are supplying raw mtl. i.e. subcontracting for 250 pcs.

To other vendor no raw raw mtl is provided we are procuring directly 250 pcs.

Now the requirement is that after running MRP the system should generate the req. of 1000 pcs. of finished good with the dependent req. of raw material for 750 pcs. only because 250 pcs. we are procuring directly from vendor.

My query is that is it possible to provide both functionality of subcotracting & direct procurement in external procurement.





It's very much possible..

you just need to maintain your quota arrangement carefully and system will consider all the things..

It'll only plan for BOM componenet for Inhouse Production and subcontracting only..not for direct purchase..

Pl maintain quota rrangement in MEQ1 and when you run MRP ,it'll act accordingly..

infact i am also using the same scenario..

Pl come back if you have further question

rewards will be appriciated if found useful answer