how to transfer dcs from one track to another

Former Member
0 Kudos

hi

can any one please tell me if it is possible to transfer dcs developed in one track to another.

regards

vln

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi Lakshmi,

I believe there is no direct way of transferring DC's from one Dev Config to another. You will have to do some manual activities for this.

Regards

Sidharth

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I suggest to you go through Scenario-3 Layered development,any how you can't directly transfer Dc's from one track to another.

Regards,

RK

Former Member
0 Kudos

hi

thanks to both of you. can you please send me any doc or explain how i can handle this scenario in any indirect way.

regards

vln

Former Member
0 Kudos

Hi,

Refer these links

1)http://help.sap.com/saphelp_nw04/helpdata/en/01/9c4940d1ba6913e10000000a1550b0/content.htm. (Scenarios)

see Scenario-3

2) Additionally go through these

Development Component (JDI)

http://help.sap.com/saphelp_erp2004/helpdata/en/34/6b63c1a7ba6845b85239999b7061bc/frameset.htm (Creating webdynpro DC)

http://help.sap.com/saphelp_erp2004/helpdata/en/9e/1c200ac164cf4a942f2dacdf3359e9/frameset.htm (Migrating Local webdynpro projects)

http://help.sap.com/saphelp_nw04/helpdata/en/49/d0ae143e94774a9423ca8c009dc76f/frameset.htm (development components)

Hope this info helped you.

Regards,

RK

0 Kudos

Hi Lakshmi,

All yu have to do is a create a DC in the new Dev Config and then in the package explorer view manually copy and paste the packages and the files from the old DC to the new one.

Hope this is helpful.Do let me know if you are not able to do the same i will then send some screenshots if you want.

Regards

Sidharth

Former Member
0 Kudos

I have a question pertaining to this.

Can you copy the Software Components from one track to another in scenario 2+?

If yes, then all the DCs belonging to that SC get copied automatically.

Is my understanding correct? or there is no direct way to copy the SC from one track to another?

Thanks,

Kiran

Former Member
0 Kudos

Hi,

Scenario 2+ concentrates on Single track,Scenario 3 is the right choice for you.

Regards,

RK

former_member183805
Active Participant
0 Kudos

Hi Kiran,

The way to "copy" SCs from one track to another is to transport them by a "forward" operation. You first need to Assemble and Approve the SCs in the source track, and then Forward the SCs to the target track. You can find the Forward button in the "History" view of the Approval Tab (in CMS Transport Studio).

I'm currently writing an article that explains some branching patterns and use-cases (and this topic is explained in greater detail). It should be available this week - I'll update this thread once it is published.

Regards,

Manohar