cost plan does not change when remove the material component, why?

My project is builded as following

<b>wbs</b>: T-20051.3

<b>activity</b>: 3000

<b>material componet</b>: T-20100

<b>material componet</b>: T-20210

  • activity is assigned to wbs, two material is assigned to activity.

<b>T-20100 and T-20210 procurement type</b> :Requisition + reservation for WBS elemen

I look cost planned report use following transaction:

S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned

cost planned of Activity 3000 is 130460 EUR,

this value is exactly equal to sum between material T-20100 cost planned and

material T-20100 cost planned that is calculated by quantity multiplied standard price.

after I delete material component T-20100 and T-20210, as a result, the cost planned of activity 3000 is not changed, that is, it value is still 130460 EUR,

I think its value should become to zero. why not be changed ? can you tell me?

thank you expert.