Hi All
How to set a wastage % , while creating a BOM.
Hi,
Wastage, you can consider as a scrap.
In CS02 basic data tab page, you can give input for operation scrap or component scrap.
Operation scrap means wherever use this bom, it will consider scrap % .
Component scrap means for this particular bom only, it will consider scrap%.
Reward if useful.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
BOM is Created for know the component used in making the particular product.
Eg: PEN is the product
Component for that is
1.Refil 1 pc
2.Body - 2 pcs
3.Cap - 1 pc
This is what you will be giving it in BOM. Wastage % will not be given in BOM.
Wastage % will be given in MRP.
Reward if use ful.
Regards,
pherasath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.