on 11-27-2007 5:02 AM
Hi
Can a version of CK11n be created that will allow a user to run the T-code to view what material would cost at without allowing them to save mark and release the estimate?
Thanks,
Nivi
Not a version of CK 11N, but creat a costing variant to make this limitation.
Copy your "standard" costing variant (the one you use to save, mark and release)
and change the Costing type selection for "price update Material Master" to "no Update"
We did this to allow the engineers to calculate cost, but to not allow them to mark and release.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.