on 11-26-2007 7:52 PM
Hi,
We are creating one inspection lot from PM order after releasing the order. Is it possible to create one notification by the system once inspection lot is created. This notification should be created by the system after inspection lot is created. This should not be through result recording. Please help.
BR
Manoj
Hi Manoj,
Notification cannot be activated automatically. You need to record defects only then you can use the notification component of QM. You need to record the defects at Inspection lot level or operation or chearacteristic level and against that defect activate the notification. You can activate the notification for critical defect class. For this you need to check the IMG. So, these are the options available to you. There is no need to go to results recording screen. You can do it through QF11 - defects recording or QA32. Else you need to create manually through QM01, as our friend said.
Reward if cleared and close the thread.
Keerthi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use tcode QM01 for creating notification.
Select notification type in the initial screen.
Give the input of material no, reference material doc,vendor, coordinator, Reason for rejection in the corresponding tab page.
Reward if useful.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.