cancel
Showing results for 
Search instead for 
Did you mean: 

Changing Price Control S to V

Former Member
0 Kudos

Hi

Currently we have Price Control as S in the System for the Trading Finished Goods

I need to change it V.....

Before Changing it the Price control form S to V I just whated to confirm what would be the impacts in calculation of Cost.

Regards

Ash

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

once u change price control from S TO V system will start calculating moving average price.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

U can change price control at any time also if stock exist for that material

Check SAP help for this

http://help.sap.com/erp2005_ehp_02/helpdata/en/47/60ff6249f011d1894c0000e829fbbd/frameset.htm

Vishal...

Former Member
0 Kudos

Hi

If you have a Standard price control to your material, Then at the time of changing the from S to V , The standard price of the material is adopted to the MAP value. This ensures that the stock value remains the same.

Award points if useful

Thanks & Regards

Kishore

Former Member
0 Kudos

u can do it in MM02 accounting view

and for valu

by mr21

u put the same price ie standred price = mav so that the value will be same