MNT ordr can not generated ins lot

siddheshwar_rajguru2
Active Participant
0 Kudos

I am crtd

1. Equipmet 2. maint plan with Ins point and sampling procedure 4, task list etc.

But when I REL MNT ordr it gives error that Ins lot can not be generated coz ins point are not defined in Mnt plan, but ins point 300 are assigned in the MNT plan.

what is the reason , that lot is not created in th system,

can u plz tell me?

Regds

Siddhesh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi siddhesh,

have you assigned the inspection type for that order in customization field. also check whether the task list has inspection characteristic and it has the status released.

kindly post the detailed error message

regards

thyagarajan

siddheshwar_rajguru2
Active Participant
0 Kudos

Diagnosis

An inspection type has been defined for the order type in question. An inspection lot should be generated when the order is released. No inspection point field combination has been defined in any of the maintenance task lists used in the order. This is why no insepction lot can be generated.

Procedure

If an inspection lot is to be created, the order must contain at least one procedure which was taken from a maintenance task list and which has been define for one of the inspection point field combinations. This must be done before the order is released.

former_member187991
Active Contributor
0 Kudos

hi siddhes

kindly check the following reasons

This example shows how the system responds when it creates an inspection lot, depending on which planning activities were completed.

The first table below provides an overview of several examples (cases) in which different combinations of planning steps were completed. The second table shows how the system responds in each case.

Planning Steps Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7

Was the inspection type assigned to the order type?

No Yes Yes Yes Yes Yes Yes

Was the maintenance task list assigned to an order?

- No Yes Yes Yes Yes Yes

Did you specify the field combination for inspection points in the maintenance task list?

- - No Yes Yes Yes Yes

Does the control key for the operation specify inspection characteristics?

- - - No No Yes Yes

Have inspection points been assigned to the operation?

- - - No Yes No Yes

See 1 See 2 See 3 See 4 See 5 See 6 See 7

Case / Item

System response

1 The inspection lot is not created.

2 The inspection lot is not created and the system records the status ILNC (inspection lot not created) in the maintenance order.

3 The system creates the inspection lot and records the status ILCR (inspection lot created) in the maintenance order. In addition:

The maintenance task list is assigned to the inspection lot.

Inspection characteristics are not created.

In this case, maintain the inspection point in the maintenance task list; then call up the function to change an inspection lot to create the inspection specifications.

4 The system creates the inspection lot and records the status ILCR (inspection lot created) in the maintenance order. In addition:

The system does not create inspection characteristics.

You can create unplanned inspection characteristics.

5 The system creates the inspection lot and records the status ILCR (inspection lot created) in the maintenance order. In addition:

The system creates inspection characteristics.

The system sets the status ICHA (planned inspection characteristics assigned) in the operation specified in the maintenance order.

The operation in the selection screen for results recording is highlighted and printed on inspection instruction.

You can create unplanned inspection characteristics.

6 The system creates the inspection lot and records the status ILCR (inspection lot created) in the maintenance order. In addition:

The system does not create inspection characteristics.

The operation in the selection screen for results recording is highlighted and printed on inspection instruction.

You can create unplanned inspection characteristics.

7 The system creates the inspection lot and records the status ILCR (inspection lot created) in the maintenance order. In addition:

The system creates inspection characteristics.

The system sets the status ICHA (planned inspection characteristics assigned) in the order operation.

The operation in the selection screen for results recording is highlighted and printed on inspection instruction.

You can create unplanned inspection characteristics.

regard